Building the foundations for future growth
The infrastructure behind a successful development is every bit as important as the buildings it supports.
At Milton Keynes East, our involvement in the Primary Street and Primary Street North 2 works encompasses a wide-ranging package of highway construction and supporting civil engineering infrastructure, helping establish the essential connections required to serve a growing development.
Bringing together highways, earthworks, drainage, utilities, street lighting and environmental works, the project demonstrates our ability to coordinate complex construction activities and deliver the interconnected infrastructure that makes development possible.
The challenge: complexity beneath and beyond the road
Major infrastructure projects demand more than effective construction. They require detailed planning, careful sequencing and the coordination of multiple disciplines working within a shared environment.
At Milton Keynes East, the works involve the integration of new highway infrastructure with existing and proposed utility networks, the protection of existing services and the management of construction interfaces.
Maintaining traffic on the A509 London Road added another important dimension, requiring temporary traffic management, traffic controls and agreed diversion arrangements to manage the impact of the works.
The challenge was to coordinate these activities as part of a joined-up infrastructure package, while maintaining focus on safe, efficient construction and the needs of the wider development.
Our solution: an integrated infrastructure approach
Our scope brings together the key civil engineering and highway disciplines needed to establish a functioning road network and its supporting infrastructure.
Highways and road construction
Construction of carriageways, the Primary Street, school access road and health hub access road, together with footways, kerbing, pavement layers and associated paved areas.
Earthworks and ground engineering
Site clearance, earthworks, ground preparation, capping and sub-grade improvement to establish the required foundations for the new infrastructure.
Drainage and underground infrastructure
Installation of surface water drainage and associated infrastructure, coordinated with the wider highway construction programme.
Utilities and service coordination
Management of interfaces with existing and new utility networks, including service diversions, supplies, ducts and connections. Careful sequencing helps address potential clashes and protect existing services.
Highway finishes and systems
Carriageway surfacing, anti-skid treatments, road markings, signage and street lighting to complete the highway infrastructure.
Environmental and landscaping works
Ground preparation, grass and wildflower establishment, landscaping-related provisions and ecological measures incorporated into the wider works.
Traffic and construction management
Coordination of construction activities and temporary traffic arrangements, including measures to maintain traffic on the A509 London Road.
The impact: infrastructure that enables development
The significance of this project lies in the integration of multiple infrastructure disciplines into one coordinated programme of works.
The resulting infrastructure framework is intended to support:
• Improved connectivity through new highway routes and access infrastructure.
• Access to key destinations including the school and health hub.
• Essential utility provision through coordinated underground services and connections.
• A functional highway network supported by drainage, lighting, signage and road markings.
• Future development through the delivery of the infrastructure needed to support the wider Milton Keynes East scheme.
This is the type of complex, interconnected infrastructure delivery where effective planning, technical coordination and practical construction expertise make a difference.
Demonstrating the strength of our delivery capability
Milton Keynes East showcases the breadth of our civil engineering and infrastructure capability. From initial ground preparation and earthworks through to drainage, utilities, highway construction and final surfacing, the project brings together the specialist activities required to deliver major infrastructure packages.
It demonstrates our ability to manage complex construction interfaces, coordinate multiple workstreams and contribute to the delivery of infrastructure that supports places, communities and long-term development.
ENGINEERING THE CONNECTIONS THAT MOVE DEVELOPMENT FORWARD.
- Full construction of 2 number Pump Stations from earthworks to handover, one at 10m depth and one at 8.5m depth including ancillary Weholite storage tanks
- Full construction of a Substation compliant with UKPN specification including brickwork and roofing
- Cut and Fill of 54,000m3
- Installation of 2,674m of Foul Water Drainage
- Installation of 2,289m of Storm Water Drainage
- Installation of 2,000m of Multi-Utility Trench
- Installation of 275m of High Pressure Rising Main
- Construction of 7,110m2 of Carriageway to Milton Keynes Highways Specification
- Construction of 5,211m2 of Adoptable Footpaths / Redways to Milton Keynes Highway Specification