Works continue to progress at the Barnsbury Estate redevelopment, where our team is delivering a 5-storey high-reach demolition as part of a carefully planned and phased programme of works.
The project scope encompasses a comprehensive package of enabling and demolition works, including full soft strip operations, licensed asbestos removal, formation of the pile mat, bulk excavation and muck away, together with the installation of sheet piling to prepare the site for the next phase of development.
With multiple workstreams being managed simultaneously, careful coordination and planning have been essential to maintaining programme efficiency while upholding the highest standards of safety and environmental management. Our experienced team continues to deliver each phase methodically, ensuring works are completed safely, efficiently, and in accordance with project requirements.
This project represents another significant milestone in the transformation of the Barnsbury Estate, showcasing our technical expertise and ability to deliver complex demolition and enabling works within a demanding urban environment.
- Removal of asbestos
- Soft strip
- Full Structural demolition
- Removal of substructure
- Cut and fill
- Forming of pile mats
- Sheet piling